Enterprise Adding Capacity At Facility Underway Near Orla

January 4, 2018

 

Enterprise Products Partners L.P. is adding 300 million cubic feet per day of incremental capacity at its cryogenic natural gas processing facility under construction near Orla, Texas in Reeves County.

The addition of a third processing train at Orla would increase inlet volume capacity to 900 MMcf/d and allow Enterprise to expand its natural gas liquids (“NGL”) extraction capabilities by an incremental 40,000 barrels per day (“BPD”) to 120,000 BPD.

The third processing train is expected to begin service in the second quarter of 2019 and will complement trains one and two, which are on schedule for completion in the second and third quarters of 2018, respectively.

Enterprise said its mixed NGLs from Orla will be delivered into Enterprise’s fully integrated pipeline system, including the new Shin Oak Pipeline currently under construction and expected to begin operations in the second quarter of 2019.